Wednesday, October 7, 2009

Phase III Roof Replacement ~ Units 1 - 4

PCTH Owners (1, 3, 4) and Timeshare Owners (Unit 2),

As detailed on the "What to Expect" document, the Phase III Roof Replacement will commence on units 1-4 starting Monday, October 12, 2009 and will likely take until Wednesday to complete.

Please note that the area around affected buildings will be treated as a construction site with limited access for safety reasons. Please take reasonable measures within your home to protect valuables on shelves and hanging on walls as recommended in the attached document and also noted below:

“Remove all loose items from shelving and walls, pictures, mirrors, plates, figurines, etc. Hammering may create vibration that could shake these items off the shelves and walls.”

In advance of the roof replacements, the chimney enclosures located on the roof will have the stucco replaced with hardi-board and repainted to match the existing color. Making these siding upgrades prior to the roof replacement will limit the amount of foot traffic required on the roof once it is complete.

We are scheduling some project work "out of order" from what was originally planned, but we are trying to earmark available funds to buildings with less roof surface and will work back towards the larger buildings as funds are available.